Vista da Usina de Colider

Updates on the Colíder Hydropower Plant

Refilling plan successfully executed and water level at colíder hydropower plant reservoir restored to 272 meters

AXIA Energia has successfully completed the refilling of the Colíder Hydropower Plant reservoir. The water level has been restored to approximately 272 meters above sea level, returning to the same level recorded in August 2025.
 

The procedure was carried out gradually and in a controlled manner, in line with the plan established by the company.
 

Throughout the process, priority was given to the safety of people, the environment, and the asset. The operation was monitored by the relevant authorities and was completed without incidents.

Placeholder

Channels for more information

Actions

Vista superior do vertedouro de Colider

River level

Based on the recommendation of a panel of experts, the company initiated the controlled drawdown of the reservoir on august 14. now, following guidance from these experts, the drawdown has been suspended.

Frequently asked questions

Background desktop

Commitment to Safety and Best Practices

All dams operated by AXIA Energia for power generation have Dam Safety Plans (PSB), submitted to the relevant authorities in accordance with current legislation. The company adopts best practices in dam safety, and its structures are recognized as a national and international benchmark.

In addition, AXIA Energia actively participates in technical discussions on the subject and supports key organizations in the field, such as the Brazilian Committee on Dams (CBDB) and the International Commission on Large Dams (ICOLD).

This engagement reinforces its ongoing pursuit of technical excellence and innovation in dam management.